Columbia's City Council unanimously approves a $35 million electric transmission line

The Daily Columbia teamFrom today’s edition · 1 min read · 4 sources

ShareEmailFacebookX

If you live near Scott Boulevard, Nifong Boulevard or Grindstone Parkway, this one's close to home. The City Council voted unanimously Monday to move ahead with a 161-kilovolt line between the Perche Creek and Grindstone substations, after input from around 20 residents.

Utilities will now look for an engineering firm to design the line. Public comment was divided, and most speakers opposed it, citing homes and schools, including Mill Creek Elementary.

The chosen route was estimated to cost less than the Chapel Hill Road option

Source: ABC17NEWS

View as table
Value
Scott-Grindstone route$30.1 million
Chapel Hill Road route$40.7 million
  • Route: 7.7 miles via Scott, Vawter School, Nifong, Grindstone
  • Funding: $29.8 million from 2015 bonds, $5.08 million from reserves
  • Timeline: eight to 10 years to design and build
  • Already spent: $24 million on the project

The city's pitch is reliability. The city says the chance of , which means shutting off power to some neighborhoods, is currently less than 1% in any given hour, and it expects that risk to grow. Those documents also say paying for the bonds will take a rate adjustment.

The transmission line has been in the works for nearly two decades

  1. 2007Initial route studies began.
  2. 2013Council approved the Scott-Vawter-Nifong-Grindstone route.
  3. 2015Voters approved revenue bonds for the project.
  4. 2016Project paused after public concerns and a lengthy hearing.
  5. 2018City brought in a task force to evaluate alternatives.
  6. Feb. 2026Staff presented updated cost estimates to the council.
  7. Nov. 16Council voted unanimously to move to engineering and design.

Source: ABC17NEWS

Sources: ABC17NEWS, Columbia Missourian, KRCG, komu.com

Read it in the full edition

More from today’s edition

Read the edition
All city hall news
  1. KXEO5 hours ago

    Columbia Gets $970K for Downtown Barricades, on KXEO

    Columbia is receiving 970-thousand dollars in state funding to help pay for a new barricade system for downtown events. City Council voted unanimously to accept the grant from the Missouri Department of Public Safety. The barricades would be used to close streets during large events and improve public safety. City officials say the funding will

  2. KJLU 88.9 FM6 hours ago

    JC Council approves outdoor storage yard, Columbia approves transmission line project, on KJLU 88.9 FM

    The Jefferson City Council approves a permit to allow an outdoor storage yard on the west end of town.

  3. KOMU 813 hours ago

    Columbia to receive nearly $1 million for downtown barricades, on KOMU 8

    Columbia downtown barricades receive $970,000 in state funding for new barricades to block off streets for large downtown events.

    Also reported byABC17NEWS