Columbia's City Council unanimously approves a $35 million electric transmission line
The Daily Columbia team
If you live near Scott Boulevard, Nifong Boulevard or Grindstone Parkway, this one's close to home. The City Council voted unanimously Monday to move ahead with a 161-kilovolt line between the Perche Creek and Grindstone substations, after input from around 20 residents.
Utilities will now look for an engineering firm to design the line. Public comment was divided, and most speakers opposed it, citing homes and schools, including Mill Creek Elementary.
The chosen route was estimated to cost less than the Chapel Hill Road option
Source: ABC17NEWS
View as table
| Value | |
|---|---|
| Scott-Grindstone route | $30.1 million |
| Chapel Hill Road route | $40.7 million |
- Route: 7.7 miles via Scott, Vawter School, Nifong, Grindstone
- Funding: $29.8 million from 2015 bonds, $5.08 million from reserves
- Timeline: eight to 10 years to design and build
- Already spent: $24 million on the project
The city's pitch is reliability. The city says the chance of load shedding, which means shutting off power to some neighborhoods, is currently less than 1% in any given hour, and it expects that risk to grow. Those documents also say paying for the bonds will take a rate adjustment.
The transmission line has been in the works for nearly two decades
- 2007Initial route studies began.
- 2013Council approved the Scott-Vawter-Nifong-Grindstone route.
- 2015Voters approved revenue bonds for the project.
- 2016Project paused after public concerns and a lengthy hearing.
- 2018City brought in a task force to evaluate alternatives.
- Feb. 2026Staff presented updated cost estimates to the council.
- Nov. 16Council voted unanimously to move to engineering and design.
Source: ABC17NEWS
Sources: ABC17NEWS, Columbia Missourian, KRCG, komu.com