Columbia City Council approves the south Columbia transmission line, and residents say they're not done
The Daily Columbia team
If you live along Scott Boulevard, Vawter School Road, Nifong Boulevard or Grindstone Parkway, this one's close to home. Columbia City Council voted unanimously Monday to move ahead with a 161-kilovolt line linking the Perche Creek and Grindstone substations. The Utilities Department will now look for an engineering firm to design the final path.
The transmission line project stalled in 2016 and restarted in 2024
- Sept. 2009The line is first introduced to the council.
- 2015Bond approval for funding comes.
- 2016Council halts progress, citing public concerns and possible alternatives.
- 2024Development on the project picks back up.
- Nov. 16Council unanimously approves the project.
Source: KBIA
Opponents aren't done. Keary Husain wants long-term health studies and a look at routes beyond the cheapest, and a petition with 478 signatures went to the council Monday. Mayor Barbara Buffaloe wrote on Facebook: "There will be additional engineering, design work, and opportunities for community engagement before anything is built."
- Route runs past Mill Creek Elementary
- Council requested a staff report on the project's history
- Petition asks for a different, less disruptive path
Utilities spokesperson Jason West said final site design approval alone could take five to seven years. City officials say the line is needed to improve power reliability and support growing demand. Want a say? We'd watch for the community engagement Buffaloe promised.
The line would run 7.7 miles and take eight to 10 years
- $35 million
- line cost, which reports describe as nearly that
- 7.7 miles
- of route along four streets
- 478
- petition signatures given to the council Monday
- 8 to 10 years
- to finish, per Utilities Director Erin Keys
Sources: ABC17NEWS, KOMU 8, KBIA, kjluradio.com