MizzouTop story
UM curators approve $95 million in Mizzou projects, led by a new electrical substation
The electrical project is most of the $95 million
Source: KOMU 8
View as table
| Amount | Share | |
|---|---|---|
| Electrical substation and lines | $80 million | 84.2% |
| McDavid Hall renovation | $15 million | 15.8% |
The University of Missouri System Board of Curators unanimously approved two campus projects totaling $95 million on Thursday: an $80 million electrical substation and transmission line project, and a $15 million renovation of McDavid Hall.
The new substation will go south of Stadium Boulevard and east of Champions Drive, replacing the one near Monk Drive and Hospital Drive. The board earlier approved $49 million to replace it at a different location, but bids exceeded that budget as costs and demand for electrical components rose. University officials project campus demand will exceed the power plant's 54-megawatt maximum by 2030.
MU's electricity need is close to what its power plant can make
50 MWMU's current electricity need, in megawatts
Source: KOMU 8
View as table
| Value | |
|---|---|
| MU's current electricity need, in megawatts | 50 MW |
| Power plant's maximum capacity | 54 MW |
- Substation expected to be finished: April 2029
- McDavid Hall: becomes home for Psychological Sciences
- Board chair Todd Graves reelected; Robert Blitz vice chair
Separately, the board approved a project to develop about 5,000 square feet of MURR West, a 47,000-square-foot facility at the University of Missouri Research Reactor, into an incubator for up to four radiopharmaceutical startup companies.